Duke-326
74.9 MW generation in Osceola, FL · In queue since May 2023 · Proposed COD December 2026
74.9 MW
Capacity
1
Components
Solar
3 years
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-31
Duke-326 is a proposed solar generation project located in Osceola County, Florida, with a total capacity of 74.9 MW. The project is being developed by Duke Energy Florida, LLC and is interconnected to the Duke Energy Florida system at the Whippoorwill Switching Station 230 kV.
The project is currently active in the Duke Energy interconnection queue, having entered the queue on May 1, 2023. The proposed commercial operation date is December 31, 2026, and the Interconnection Agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Osceola
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Whippoorwill Switching Station 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.