Duke-328
172 MW generation in Pinellas, FL · In queue since June 2023 · Proposed COD November 2023
172 MW
Capacity
1
Components
Gas
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
5 months
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-28
Duke-328 is a proposed 172 MW gas-fired generation project located in Pinellas County, Florida. The project is being developed by Duke Energy Florida, LLC, and is interconnected to the Bartow Plant Substation at 230 kV.
The project is listed in the Duke Energy Florida interconnection queue with an entry date of June 6, 2023. The proposed commercial operation date is November 28, 2023, and the interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
FL
County
Pinellas
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Bartow Plant Substation 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.