Duke-329
74.9 MW generation in Hamilton, FL · In queue since June 2023 · Proposed COD December 2025
74.9 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
Duke-329 is a proposed solar generation project located in Hamilton County, Florida, with a total capacity of 74.9 MW. The project, being developed by Duke Energy Florida, LLC, entered the Duke Energy Florida interconnection queue on June 15, 2023, and has a proposed commercial operation date of December 1, 2025. The point of interconnection is the Suwannee River - Pine Grove (GA PWR) 230 kV line.
The interconnection agreement status for Duke-329 is currently listed as suspended. The project consists solely of solar photovoltaic generation, with the 74.9 MW capacity attributed to this technology.
Generated from interconnection queue and public data sources
State
FL
County
Hamilton
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Suwannee River - Pine Grove (GA PWR) 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.