Duke-42
10 MW generation in Citrus, FL · In queue since December 2006 · Proposed COD November 2008
10 MW
Capacity
1
Components
Other
19y 5m
In Queue
IA Executed
IA Status
COD target: 2008
Total Duration
1y 11m
Schedule
213 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2008-11-01
Duke-42 is a proposed 10 MW generation project located in Citrus County, Florida. The project, developed by Duke Energy Florida, LLC, utilizes an unspecified "Other" technology. It is interconnected to the Crystal River Substation.
The project entered the Duke Energy Florida interconnection queue on December 11, 2006, and has an Interconnection Agreement (IA) executed. The proposed commercial operation date (COD) is November 1, 2008. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
FL
County
Citrus
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Crystal River Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.