Project Duke-5 — Project Summary

Queue ID
Duke-5
Capacity
480 MW
Technology
Gas
Status
active
Location
Pasco, FL
Region
Southeast
Developer
IA Status
IA Executed

Duke-5

Duke-5BetaActiveGasDukeLBNL

480 MW generation in Pasco, FL · In queue since October 1999

480 MW

Capacity

1

Components

Gas

26y 7m

In Queue

IA Executed

IA Status

Interconnection

Total Duration

26y 7m

Construction75%
Queue EntryOct 28, 1999

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Commercial operation date not yet determined

About

Duke-5 is a proposed 480 MW gas-fired generation project located in Pasco County, Florida. The project, developed by Duke Energy Florida (entity: Duke), entered the utility's interconnection queue on October 28, 1999. The point of interconnection is the Hudson Substation 230 kV.

The project's interconnection agreement (IA) has been executed. The project is listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

FL

County

Pasco

Grid Region

Southeast

Market

Developer

Utility

Duke Energy Florida

Entity

Duke

Service Type

Point of Interconnection

Hudson Substation 230 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
FRCC
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.