Duke-50
35 MW generation in Polk, FL · In queue since January 2007 · Proposed COD December 2007
35 MW
Capacity
1
Components
Other
19y 4m
In Queue
IA Executed
IA Status
COD target: 2007
Total Duration
11 months
Schedule
224 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2007-12-01
Duke-50 is a proposed 35 MW generation project located in Polk County, Florida. The project, developed by Duke Energy Florida, LLC, utilizes an unspecified "Other" technology. It is interconnected to the Duke Energy Florida system at the Hines Substation.
The project entered the Duke interconnection queue on January 12, 2007, with a proposed commercial operation date of December 1, 2007. An Interconnection Agreement (IA) has been executed for the project, and its queue status is currently listed as active.
Generated from interconnection queue and public data sources
State
FL
County
Polk
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Hines Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.