Duke-561350
4.6 MW storage in Fairfield, SC · In queue since June 2022 · Proposed COD September 2025
4.6 MW
Capacity
1
Components
Battery
3y 11m
In Queue
Construction
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-15
Duke-561350 is a proposed 4.6 MW battery storage project located in Fairfield County, South Carolina. The project, being developed by Duke Energy Carolinas, consists of a single 4.6 MW battery component. It is currently listed as active in the Duke Energy Carolinas interconnection queue, with an entry date of June 1, 2022, and a proposed commercial operation date of September 15, 2025. The project's interconnection agreement status is currently listed as "Construction".
The point of interconnection for Duke-561350 is the Longtown Ret substation.
Generated from interconnection queue and public data sources
State
SC
County
Fairfield
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Longtown Ret
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-561350