Duke-563202
2.667 MW storage in Burke, NC · In queue since June 2022 · Proposed COD September 2025
2.667 MW
Capacity
1
Components
Battery
3y 11m
In Queue
Construction
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-15
Duke-563202 is a proposed 2.67 MW battery storage project located in Burke County, North Carolina. The project, being developed by Duke Energy Carolinas, entered the interconnection queue on June 1, 2022, and has a proposed commercial operation date of September 15, 2025. The point of interconnection is at Nebo Ret.
The project is currently in the construction phase of its interconnection agreement within the Duke Energy Carolinas queue. Recent news coverage has discussed Duke's battery storage buildout in the Carolinas.
Generated from interconnection queue and public data sources
State
NC
County
Burke
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Nebo Ret
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-563202