Duke-563648
115 MW storage in Gaston, NC · In queue since June 2022 · Proposed COD December 2027
115 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-12-31
Duke-563648 is a proposed 115 MW battery storage project located in Gaston County, North Carolina. The project, developed by Duke, is interconnected with Duke Energy Carolinas. It entered the interconnection queue on June 3, 2022, with a proposed commercial operation date of December 31, 2027. The project's interconnection agreement has been executed.
The project consists of 115 MW of battery storage capacity. The point of interconnection is STONEWATER TIE. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NC
County
Gaston
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
STONEWATER TIE
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.