Duke-566170
56 MW storage in Wake, NC · In queue since June 2022 · Proposed COD December 2026
56 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-12-31
Duke-566170 is a proposed 56 MW battery storage project located in Wake County, North Carolina. The project, under development by Duke Energy Progress, LLC, consists of a single 56 MW battery component. It is interconnected to the Duke Energy Progress system at the NEW HILL 230KV TAP LINE.
The project is listed in the Duke Energy interconnection queue with an entry date of June 14, 2022, and a proposed commercial operation date of December 31, 2026. The interconnection agreement (IA) for the project has been executed.
Generated from interconnection queue and public data sources
State
NC
County
Wake
Grid Region
Southeast
Market
—
Developer
Duke Energy Progress, LLC
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
NEW HILL 230KV TAP LINE
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.