Duke-566488
74.9 MW generation in Chesterfield, SC · In queue since June 2022 · Proposed COD December 2026
74.9 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Construction
IA Status
COD target: 2026
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
Duke-566488 is a proposed 74.9 MW solar generation project located in Chesterfield County, South Carolina. The project is being developed by Duke and is interconnected to the Duke Energy Progress system. It entered the interconnection queue on June 29, 2022, with a proposed commercial operation date of December 1, 2026. The project's interconnection agreement status is currently listed as "Construction".
This development project is in the Southeast region and connects to the ROBINSON PLANT - ROCKINGHAM 230KV point of interconnection.
Generated from interconnection queue and public data sources
State
SC
County
Chesterfield
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
ROBINSON PLANT - ROCKINGHAM 230KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.