Duke-566580
60 MW generation in Lee, SC · In queue since June 2022 · Proposed COD December 2026
60 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Pending
IA Status
COD target: 2026
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
Duke-566580 is a proposed 60 MW solar generation project located in Lee County, South Carolina. The project is being developed by Duke and is interconnected with Duke Energy Progress. It entered the interconnection queue on June 29, 2022, with a proposed commercial operation date of December 1, 2026. The project's interconnection agreement status is currently listed as "IA Pending".
This development project is listed in the interconnection queue of the regional transmission organization serving the Southeast. The point of interconnection is the ROBINSON PLANT - SUMTER 230KV.
Generated from interconnection queue and public data sources
State
SC
County
Lee
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
ROBINSON PLANT - SUMTER 230KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN