Duke-569014
48 MW generation in Kershaw, SC · In queue since June 2022 · Proposed COD September 2027
48 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-10
The proposed Duke-569014 project is a 48 MW solar generation project located in Kershaw County, South Carolina. The project is being developed by Duke and is interconnected with Duke Energy Progress. It entered the utility's interconnection queue on June 30, 2022, and has a proposed commercial operation date of September 10, 2027. The interconnection agreement for the project has been executed.
The point of interconnection for the Duke-569014 project is the ROBINSON PLANT - CAMDEN JUNCTION 115KV.
Generated from interconnection queue and public data sources
State
SC
County
Kershaw
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
ROBINSON PLANT - CAMDEN JUNCTION 115KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-569014