Duke-569164
70.7 MW generation in Newberry, SC · In queue since June 2022 · Proposed COD December 2027
70.7 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-01
Duke-569164 is a proposed solar generation project with a total capacity of 70.7 MW, located in Newberry County, South Carolina. The project is being developed by Duke and is interconnected to Duke Energy Carolinas via the Champion Bl 100 kV point of interconnection.
The project is listed in the Duke Energy Carolinas interconnection queue with an entry date of June 24, 2022. Its proposed commercial operation date is December 1, 2027, and the Interconnection Agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
SC
County
Newberry
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Champion Bl 100 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN