Duke-569890
80 MW generation in Wayne, NC · In queue since June 2022 · Proposed COD August 2026
80 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-08-15
Duke-569890 is a proposed 80 MW solar generation project located in Wayne County, North Carolina. The project is being developed by Duke and is interconnected with Duke Energy Progress. It consists of 80 MW of solar photovoltaic generation.
The project entered the Duke Energy Progress interconnection queue on June 29, 2022, with a proposed commercial operation date of August 15, 2026. The interconnection agreement for the project has been executed. The point of interconnection is the LEE SUBSTATION - MT OLIVE 230KV.
Generated from interconnection queue and public data sources
State
NC
County
Wayne
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
LEE SUBSTATION - MT OLIVE 230KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-569890