Duke-572280
72 MW generation in Greenwood, SC · In queue since June 2022
72 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Pending
IA Status
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-572280 is a proposed 72 MW solar generation project located in Greenwood County, South Carolina. The project is being developed by Duke and is interconnected with Duke Energy Carolinas. It entered the interconnection queue on June 28, 2022, and its interconnection agreement status is currently listed as "IA Pending."
The proposed project is listed in the interconnection queue of an ISO/RTO in the Southeast region. The point of interconnection is the Champion Bl 100 kV substation.
Generated from interconnection queue and public data sources
State
SC
County
Greenwood
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Champion Bl 100 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-572280