Duke-58
10 MW generation in Polk, FL · In queue since January 2007 · Proposed COD May 2008
10 MW
Capacity
1
Components
Other
19y 4m
In Queue
IA Executed
IA Status
COD target: 2008
Total Duration
1y 4m
Schedule
219 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2008-05-01
Duke-58 is a proposed 10 MW generation project located in Polk County, Florida. The project, developed by Duke Energy Florida, LLC, utilizes an unspecified "Other" technology. It is interconnected to the Tiger Bay Substation within the Duke Energy Florida service area.
The project entered the Duke Energy interconnection queue on January 17, 2007, with a proposed commercial operation date of May 1, 2008. An Interconnection Agreement (IA) has been executed for the project, and its status is currently listed as active.
Generated from interconnection queue and public data sources
State
FL
County
Polk
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Tiger Bay Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.