Duke-72
340 MW generation in Osceola, FL · In queue since October 2007 · Proposed COD December 2009
340 MW
Capacity
1
Components
Other
18y 7m
In Queue
IA Executed
IA Status
COD target: 2009
Total Duration
2y 2m
Schedule
200 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2009-12-01
The Duke-72 development project is a proposed 340 MW generation project located in Osceola County, Florida. The project, developed by GenOn, is interconnected with Duke Energy Florida via the Holopaw Substation. The technology is listed as "Other".
The project is in the Duke interconnection queue with an entry date of October 7, 2007, and a proposed commercial operation date of December 1, 2009. An Interconnection Agreement (IA) has been executed. The project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
FL
County
Osceola
Grid Region
Southeast
Market
—
Developer
GenOn
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Holopaw Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-72