Duke-898999
199.9 MW storage in Robeson, NC · In queue since June 2023
199.9 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Cluster Study
IA Status
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-898999 is a proposed 199.9 MW battery storage project located in Robeson County, North Carolina. The developer is masked. The project is interconnected with Duke Energy Progress and is in the Duke Energy interconnection queue, with an entry date of June 28, 2023. Its interconnection status is currently in the Cluster Study phase. The point of interconnection is the Weatherspoon Plant Station.
This development project consists solely of battery storage, with a total capacity of 199.9 MW.
Generated from interconnection queue and public data sources
State
NC
County
Robeson
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Weatherspoon Plant Station
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-898999