Duke-899759
136 MW generation in Catawba, NC · In queue since June 2023
136 MW
Capacity
1
Components
Gas
2y 11m
In Queue
IA Pending
IA Status
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-899759 is a proposed project in Catawba County, North Carolina, with a total capacity of 136 MW. The project, developed by Duke, is a gas-fired generation facility. It is interconnected to the Duke Energy Carolinas system at the Marshall Steam Station 230KV Switchyard.
The project entered the Duke Energy Carolinas interconnection queue on June 28, 2023. Its interconnection agreement (IA) status is currently listed as "IA Pending".
Generated from interconnection queue and public data sources
State
NC
County
Catawba
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Marshall Steam Station 230KV Switchyard
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.