Duke-899771
313 MW generation in Person, NC · In queue since June 2023
313 MW
Capacity
1
Components
Gas
2y 11m
In Queue
Cluster Study
IA Status
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-899771 is a proposed 313 MW gas-fired generation project located in Person County, North Carolina. The project, being developed by Duke Energy Progress, LLC, is interconnected to the Duke Energy Progress system at the Roxboro Steam Station 230 kV Switchyard. It entered the interconnection queue on June 28, 2023 and is currently in the Cluster Study phase.
This development project has been featured in recent news coverage, with three articles categorized as regulatory and industry news.
Generated from interconnection queue and public data sources
State
NC
County
Person
Grid Region
Southeast
Market
—
Developer
Duke Energy Progress, LLC
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Roxboro Steam Station 230 kV Switchyard
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26