Duke-899793
1.5 MW generation in Jackson, NC · In queue since June 2023
1.5 MW
Capacity
1
Components
Hydro
2y 11m
In Queue
IA Pending
IA Status
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-899793 is a proposed 1.5 MW hydroelectric generation project located in Jackson County, North Carolina. The project, developed by Duke, is interconnected to the Duke Energy Carolinas system. It entered the interconnection queue on June 28, 2023, and its interconnection agreement status is currently listed as "IA Pending."
The proposed project consists of 1.5 MW of hydroelectric capacity. The point of interconnection (POI) is at EAST FORK.
Generated from interconnection queue and public data sources
State
NC
County
Jackson
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
EAST FORK
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.