Duke-917443
80 MW generation in Scotland, NC · In queue since September 2023
80 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Cluster Study
IA Status
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-917443 is a proposed 80 MW solar generation project located in Scotland County, North Carolina. The project is being developed by Duke and is interconnected with Duke Energy Progress. It entered the interconnection queue on September 26, 2023, and is currently in the Cluster Study phase.
The proposed project is listed in the interconnection queue for the RAEFORD - RICHMOND SUBSTATION 230KV NORTH.
Generated from interconnection queue and public data sources
State
NC
County
Scotland
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
RAEFORD - RICHMOND SUBSTATION 230KV NORTH
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-917443