Duke-919551
40 MW generation in Lincoln, NC · In queue since September 2023
40 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-919551 is a proposed 40 MW solar generation project located in Lincoln County, North Carolina, within the Duke Energy Carolinas service area. The project, sponsored by Duke, entered the interconnection queue on September 28, 2023. Its interconnection status is currently in the Facility Study phase.
The proposed project is listed in the Duke Energy Carolinas interconnection queue as queue ID Duke-919551. It consists of 40 MW of solar capacity and is planned to connect to the grid at the Mull point of interconnection.
Generated from interconnection queue and public data sources
State
NC
County
Lincoln
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Mull
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.