Duke-920659
67 MW generation in Wayne, NC · In queue since September 2023
67 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Cluster Study
IA Status
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-920659 is a proposed solar generation project with a total capacity of 67 MW, located in Wayne County, North Carolina. The project is being developed by Duke and is interconnected with Duke Energy Progress. It entered the interconnection queue on September 30, 2023, and is currently in the Cluster Study phase.
The proposed project is listed in the Duke Energy Progress interconnection queue. The point of interconnection is the LEE SUB - WOMMACK 230KV NORTH substation.
Generated from interconnection queue and public data sources
State
NC
County
Wayne
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
LEE SUB - WOMMACK 230KV NORTH
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.