Duke-920665
74.99 MW generation in Union, SC · In queue since September 2023
74.99 MW
Capacity
1
Components
Solar
2y 8m
In Queue
IA Pending
IA Status
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-920665 is a proposed solar generation project with a total capacity of 74.99 MW, located in Union County, South Carolina. The project is being developed by Duke and is interconnected with Duke Energy Carolinas. It entered the interconnection queue on September 28, 2023, and its interconnection agreement status is currently listed as "IA Pending".
The project is located in the Southeast region. It is listed as "active" in the interconnection queue. The point of interconnection (POI) is Midway.
Generated from interconnection queue and public data sources
State
SC
County
Union
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Midway
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.