Duke-923973
275 MW generation in Richmond, NC · In queue since September 2023
275 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Cluster Study
IA Status
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-923973 is a proposed solar generation project with a total capacity of 275 MW, located in Richmond County, North Carolina. The development project, sponsored by a masked developer and interconnected with Duke Energy Progress, entered the Duke Energy interconnection queue on September 27, 2023. Its interconnection status is currently in the Cluster Study phase.
The project is planned to connect to the LAURINBURG - RICHMOND 230KV point of interconnection.
Generated from interconnection queue and public data sources
State
NC
County
Richmond
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
LAURINBURG - RICHMOND 230KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.