Duke-948720
80 MW generation in Nash, NC · In queue since June 2017 · Proposed COD July 2025
80 MW
Capacity
1
Components
Solar
8y 11m
In Queue
Construction
IA Status
COD target: 2025
Total Duration
8y 1m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-31
Duke-948720 is a proposed 80 MW solar generation project located in Nash County, North Carolina. The project, under development by Duke Energy Progress, LLC, is interconnected within the Duke Energy Progress system. It entered the interconnection queue on June 16, 2017, and has a proposed commercial operation date of July 31, 2025. Its interconnection agreement status is currently listed as "Construction".
The project consists of 80 MW of solar photovoltaic generation capacity. It is currently listed as an active project within the interconnection queue. The project has appeared in recent news coverage regarding Duke Energy's renewable energy development plans in the Southeast region.
Generated from interconnection queue and public data sources
State
NC
County
Nash
Grid Region
Southeast
Market
—
Developer
Duke Energy Progress, LLC
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.