Duke-955167
73 MW generation in NC · In queue since June 2022
73 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Executed
IA Status
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Commercial operation date not yet determined
Duke-955167 is a proposed 73 MW solar generation project located in North Carolina within the Southeast region. The project is being developed by Duke and is interconnected with Duke Energy Progress at the SELMA - WAKE 230KV point of interconnection.
The project entered the Duke Energy Progress interconnection queue on June 29, 2022. The interconnection agreement (IA) for the project has been executed.
Generated from interconnection queue and public data sources
State
NC
County
—
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
SELMA - WAKE 230KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-955167