Project Duke-956244 — Project Summary

Queue ID
Duke-956244
Capacity
99 MW
Technology
Battery
Status
active
Location
Robeson, NC
Region
Southeast
Developer
Duke Energy Progress, LLC.
IA Status
Cluster Study

Duke-956244

Duke-956244BetaActiveBatteryDukeLBNL

99 MW storage in Robeson, NC · In queue since June 2024

99 MW

Capacity

1

Components

Battery

1y 11m

In Queue

Cluster Study

IA Status

Interconnection

Total Duration

1y 11m

Impact Study25%
Queue EntryJun 19, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

Duke-956244 is a proposed 99 MW battery storage project located in Robeson County, North Carolina. The project, under development by Duke Energy Progress, LLC., entered the Duke Energy Progress interconnection queue on June 19, 2024. Its point of interconnection is the Weatherspoon Plant Substation at 230kV.

The project's interconnection status is currently in the Cluster Study phase.

Generated from interconnection queue and public data sources

Project Details

State

NC

County

Robeson

Grid Region

Southeast

Market

Developer

Duke Energy Progress, LLC.

Utility

Duke Energy Progress

Entity

Duke

Service Type

Point of Interconnection

Weatherspoon Plant Substation 230kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.