Duke-956283
110 MW generation in Chesterfield, SC · In queue since June 2024
110 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-956283 is a proposed solar generation project with a total capacity of 110 MW. The project is located in Chesterfield County, South Carolina, within the Duke Energy Progress service area. The developer is Masked. It is listed as "active" in the Duke Energy interconnection queue, with a queue entry date of June 26, 2024. The project's interconnection status is currently in the Cluster Study phase.
The proposed commercial operation date is not specified in the provided data. The point of interconnection (POI) is the Robinson Plant - Rockingham 230kV - Florence. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
SC
County
Chesterfield
Grid Region
Southeast
Market
—
Developer
Masked
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
ROBINSON PLANT - ROCKINGHAM 230KV - FLORENCE
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-956283