Duke-956475
30 MW generation in Anderson, SC · In queue since June 2024
30 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-956475 is a proposed 30 MW gas-fired generation project located in Anderson County, South Carolina. The project is being developed by Duke and is interconnected with Duke Energy Carolinas. It entered the interconnection queue on June 10, 2024, and is currently in the Cluster Study phase. The point of interconnection is the W.S. LEE COMBINED CYCLE STA 100 kV.
This proposed project is listed in the Duke Energy Carolinas interconnection queue. No proposed commercial operation date is available.
Generated from interconnection queue and public data sources
State
SC
County
Anderson
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
W.S. LEE COMBINED CYCLE STA 100 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-956475