4.5 MW generation in Florence, SC · In queue since June 2024
4.5 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed Duke-956532 project is a 4.5 MW solar generation project located in Florence County, South Carolina. The project is being developed by Duke and interconnected to the Duke Energy Progress system at the LAKE CITY 230KV point of interconnection.
The project entered the interconnection queue on June 27, 2024, and is currently in the Cluster Study phase of the interconnection process.
Generated from interconnection queue and public data sources
State
SC
County
Florence
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
LAKE CITY 230KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.