Duke-956538
75 MW generation in Marlboro, SC · In queue since June 2024
75 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-956538 is a proposed 75 MW solar generation project located in Marlboro County, South Carolina. The project, developed by Duke Energy Progress, entered the Duke Energy Progress interconnection queue on June 27, 2024. Its interconnection status is currently in the Cluster Study phase.
The proposed project consists of 75 MW of solar capacity. The point of interconnection is the Bennettsville SW Station on the Laurinburg 230kV line to Florida.
Generated from interconnection queue and public data sources
State
SC
County
Marlboro
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
BENNETTSVILLE SW STA - LAURINBURG 230KV - FLOR
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.