Duke-956747
470 MW generation in Rowan, SC · In queue since June 2024
470 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-956747 is a proposed 470 MW gas-fired generation project located in Rowan County, South Carolina. The project is being developed by Duke Energy Carolinas and consists of 470 MW of gas-fired capacity. It is currently in the Duke Energy Carolinas interconnection queue, with an entry date of June 20, 2024. The project's interconnection status is listed as "Cluster Study".
The point of interconnection for Duke-956747 is the Buck Tie Switchyard 100 kV.
Generated from interconnection queue and public data sources
State
SC
County
Rowan
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Buck Tie Switchyard 100 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-956747