Duke-956974
40 MW generation in Rockingham, NC · In queue since June 2024
40 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-956974 is a proposed 40 MW gas-fired generation project located in Rockingham County, North Carolina. The project, developed by Duke, is interconnected to the Duke Energy Carolinas system at the Dan River CTCC Station 100 kV point of interconnection.
The project entered the interconnection queue on June 11, 2024, and is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
NC
County
Rockingham
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Dan River CTCC Station 100 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-956974