Duke-957051
8.91 MW generation in Jackson, NC · In queue since June 2024
8.91 MW
Capacity
1
Components
Hydro
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-957051 is a proposed hydroelectric generation project with a total capacity of 8.91 MW. The project is located in Jackson County, North Carolina, within the Duke Energy Carolinas service area. Duke is the listed entity for the project, which interconnects at the Thorpe Hydro Substation at 161 kV.
The project is currently in the Duke Energy Carolinas interconnection queue with an entry date of June 27, 2024. Its interconnection status is listed as "Cluster Study".
Generated from interconnection queue and public data sources
State
NC
County
Jackson
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
THORPE HYDRO Substation 161 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.