Duke-957065
18 MW generation in Laurens, SC · In queue since June 2024
18 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-957065 is a proposed 18 MW solar generation project located in Laurens County, South Carolina. The project is being developed by Duke and has an interconnection point at Kinards 44 kV. It is listed in the Duke Energy Carolinas interconnection queue with an entry date of June 28, 2024. The project's interconnection status is currently in the Cluster Study phase.
The proposed project consists of 18 MW of solar photovoltaic generation. It is located in the Southeast region and is listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
SC
County
Laurens
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Kinards 44 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.