Duke-957084
25 MW generation in Darlington, SC · In queue since June 2024
25 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-957084 is a proposed solar generation project with a total capacity of 25 MW, located in Darlington County, South Carolina. The project is being developed by Duke and is interconnected with Duke Energy Progress. It entered the interconnection queue on June 29, 2024, and is currently in the Cluster Study phase.
The proposed project is listed in the interconnection queue for the Duke Energy Progress system. The point of interconnection is the ROBINSON PLANT - CAMDEN JUNCTION 115KV.
Generated from interconnection queue and public data sources
State
SC
County
Darlington
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
ROBINSON PLANT - CAMDEN JUNCTION 115KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.