Duke-957086
30 MW generation in Darlington, SC · In queue since June 2024
30 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-957086 is a proposed 30 MW solar generation project located in Darlington County, South Carolina. The project, under development by Duke Energy Progress, entered the Duke Energy interconnection queue on June 29, 2024. Its interconnection status is currently in the Cluster Study phase.
The proposed project consists of 30 MW of solar photovoltaic generation. The point of interconnection is at the DARLINGTON COUNTY PLANT - BENNETTSVILLE SW STA 230.
Generated from interconnection queue and public data sources
State
SC
County
Darlington
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
DARLINGTON COUNTY PLANT - BENNETTSVILLE SW STA 230
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-957086