Duke-957087
4.99 MW generation in Florence, SC · In queue since June 2024
4.99 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-957087 is a proposed solar generation project with a total capacity of 4.99 MW, located in Florence County, South Carolina. The project is being developed by Duke and has entered the Duke Energy Progress interconnection queue on June 29, 2024. Its interconnection status is currently in the Cluster Study phase.
The proposed project consists of 4.99 MW of solar photovoltaic generation. The point of interconnection (POI) is the OLANTA 230KV substation.
Generated from interconnection queue and public data sources
State
SC
County
Florence
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
OLANTA 230KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-957087