Duke-957241
6 MW generation in Chester, SC · In queue since June 2024
6 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-957241 is a proposed 6 MW solar generation project located in Chester County, South Carolina. The project, developed by Duke, is interconnected to Duke Energy Carolinas and entered the interconnection queue on June 27, 2024. Its point of interconnection is at E CHESTER RET.
The project's interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
SC
County
Chester
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
E CHESTER RET
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.