Duke-957264
1,485 MW generation in Anderson, SC · In queue since June 2024
1,485 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-957264 is a proposed generation project located in Anderson County, South Carolina, within the Duke Energy Carolinas service area. The project, sponsored by Duke, consists of 1485 MW of gas-fired generation. It is currently listed as active in the Duke Energy Carolinas interconnection queue, with a queue entry date of June 21, 2024. The project's interconnection status is currently in the Cluster Study phase.
The proposed project would interconnect at the Anderson Tie 230 kV. Recent news coverage has discussed Duke's plans for gas generation in the Carolinas, though specific details on this project are not available.
Generated from interconnection queue and public data sources
State
SC
County
Anderson
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
Anderson Tie 230 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.