Project Duke-957509 — Project Summary

Queue ID
Duke-957509
Capacity
33 MW
Technology
Gas
Status
active
Location
Rockingham, NC
Region
Southeast
Developer
IA Status
Cluster Study

Duke-957509

Duke-957509BetaActiveGasDukeLBNL

33 MW generation in Rockingham, NC · In queue since June 2024

33 MW

Capacity

1

Components

Gas

1y 11m

In Queue

Cluster Study

IA Status

Interconnection

Total Duration

1y 11m

Impact Study25%
Queue EntryJun 20, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

Duke-957509 is a proposed 33 MW gas-fired generation project located in Rockingham County, North Carolina. The project is being developed by Duke and is interconnected to the Duke Energy Carolinas system at the Ernest SW Station 230 kV point of interconnection.

The project entered the interconnection queue on June 20, 2024, and is currently in the Cluster Study phase of the interconnection process.

Generated from interconnection queue and public data sources

Project Details

State

NC

County

Rockingham

Grid Region

Southeast

Market

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Service Type

Point of Interconnection

Ernest SW Station 230 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project Duke-957509