Duke-957670
8 MW generation in New Hanover, NC · In queue since June 2024
8 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke Energy Progress, LLC is proposing an 8 MW gas-fired generation project, identified as Duke-957670, in New Hanover County, North Carolina. The project is interconnected to the Duke Energy Progress system at the Sutton Plant Substation 115kV.
The proposed project entered the Duke Energy Progress interconnection queue on June 24, 2024, and is currently in the Cluster Study phase of the interconnection process.
Generated from interconnection queue and public data sources
State
NC
County
New Hanover
Grid Region
Southeast
Market
—
Developer
Duke Energy Progress, LLC
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Sutton Plant Substation 115kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.