Duke-958048
10 MW generation in Spartanburg, SC · In queue since June 2024
10 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-958048 is a proposed 10 MW solar generation project located in Spartanburg County, South Carolina. The project is being developed by Duke and is interconnected with Duke Energy Carolinas. It entered the interconnection queue on June 28, 2024, and is currently in the Cluster Study phase.
The proposed project, consisting of 10 MW of solar capacity, is located in the Southeast region. The point of interconnection is at the BMW MFG Corp 100 kV substation.
Generated from interconnection queue and public data sources
State
SC
County
Spartanburg
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
BMW MFG Corp 100 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-958048