Project Duke-958048 — Project Summary

Queue ID
Duke-958048
Capacity
10 MW
Technology
Solar
Status
active
Location
Spartanburg, SC
Region
Southeast
Developer
IA Status
Cluster Study

Duke-958048

Duke-958048BetaActiveSolarDukeLBNL

10 MW generation in Spartanburg, SC · In queue since June 2024

10 MW

Capacity

1

Components

Solar

1y 11m

In Queue

Cluster Study

IA Status

Interconnection

Total Duration

1y 11m

Impact Study25%
Queue EntryJun 28, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

Duke-958048 is a proposed 10 MW solar generation project located in Spartanburg County, South Carolina. The project is being developed by Duke and is interconnected with Duke Energy Carolinas. It entered the interconnection queue on June 28, 2024, and is currently in the Cluster Study phase.

The proposed project, consisting of 10 MW of solar capacity, is located in the Southeast region. The point of interconnection is at the BMW MFG Corp 100 kV substation.

Generated from interconnection queue and public data sources

Project Details

State

SC

County

Spartanburg

Grid Region

Southeast

Market

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Service Type

Point of Interconnection

BMW MFG Corp 100 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.