Duke-961752
79.9 MW generation in Bladen, NC · In queue since September 2024
79.9 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Cluster Study
IA Status
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-961752 is a proposed solar generation project with a total capacity of 79.9 MW, located in Bladen County, North Carolina, within the Southeast region. The project is being developed by Duke and is interconnected with Duke Energy Progress. It is currently in the Cluster Study phase of interconnection, having entered the queue on September 26, 2024.
The proposed project is listed in the Duke Energy Progress interconnection queue as queue ID Duke-961752. The point of interconnection is the CUMBERLAND - DELCO 230KV substation.
Generated from interconnection queue and public data sources
State
NC
County
Bladen
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
CUMBERLAND - DELCO 230KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.