Duke-962858
74.9 MW generation in Union, SC · In queue since September 2024
74.9 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Cluster Study
IA Status
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-962858 is a proposed solar generation project located in Union County, South Carolina, with a total capacity of 74.9 MW. The project is being developed by Duke and has entered the Duke Energy Carolinas interconnection queue on September 25, 2024. It is currently in the Cluster Study phase of the interconnection process.
The point of interconnection for Duke-962858 is the JORDAN 100kV substation.
Generated from interconnection queue and public data sources
State
SC
County
Union
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
JORDAN 100kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-962858