Duke-962925
145 MW generation in Lee, SC · In queue since September 2024
145 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Cluster Study
IA Status
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-962925 is a proposed solar generation project with a total capacity of 145 MW. The project is located in Lee County, South Carolina, within the Duke Energy Progress service area. It is sponsored by Duke and interconnected at the Robinson Plant - Sumter 230kV point of interconnection.
The project entered the Duke Energy Progress interconnection queue on September 26, 2024, and its interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
SC
County
Lee
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Robinson Plant - Sumter 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-962925