74.9 MW generation in Marion, SC · In queue since September 2024
74.9 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Cluster Study
IA Status
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-962968 is a proposed solar generation project with a total capacity of 74.9 MW. The project is located in Marion County, South Carolina, within the Duke Energy Progress service area. It is sponsored by Duke and consists of 74.9 MW of solar photovoltaic generation.
The project is currently in the Duke Energy Progress interconnection queue, having entered the queue on September 27, 2024. Its interconnection status is listed as "Cluster Study".
Generated from interconnection queue and public data sources
State
SC
County
Marion
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Florence DuPont - Marion 115 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.